Shopfloor

Takt time calculator

Calculate demand pace from net production time, compare it with observed cycle time, and see the required hourly rate.

Reset example

Bookmark the result URL to keep these inputs. Use one consistent currency where applicable. Print this page for a calculation record.

Result

Inputs used

Scheduled time (min)
480
Excluded breaks (min)
30
Customer demand (units)
600
Observed cycle (sec/unit)
40
Net available time450 min
Takt time45 sec/unit
Required pace80 units/hour
Takt minus observed cycle5 sec/unit

Observed cycle meets takt on these inputs. Stops, yield and product mix can still prevent meeting demand.

From the maintainer: Understanding the Shop Floor — a practical companion to the systems behind these tools; also How to Remain Valuable When Intelligence Becomes Cheap — on staying valuable as AI and automation reshape engineering work.

FIG. 03At the inspection gate
Flow. Inspect. Improve. Work moves through an inspection station. Cycle time, stops and accepted output describe different parts of this flow; measure each separately.

Formula and worked example

Takt time = (scheduled minutes − excluded breaks) × 60 / customer demand. A 480-minute shift with 30 minutes of breaks and demand for 600 units gives 450 × 60 / 600 = 45 seconds per unit. Required pace is 80 units per net production hour. A measured 40-second cycle has five seconds of margin before losses.

Use the same period for demand and time. Do not subtract breakdowns merely to make takt easier to achieve: takt expresses customer pace. Record the planning boundary and model actual losses with the production capacity calculator or OEE calculator.

Frequently asked questions

Is takt time the same as cycle time?

Takt comes from demand; cycle time comes from observing the process. A machine can meet takt while the overall line misses delivery because of stops, rejects or an upstream constraint.

What if demand is zero?

There is no finite takt target for a zero-demand period. This tool requires positive demand rather than displaying an invented pace.

Reference

Lean Enterprise Institute: takt time defines the production-time to demand relationship. The shift example above is illustrative, not a plant benchmark.

Go deeper

Cite this page: Takt time calculator, Shopfloor. https://shopfloor.space/tools/takt-time-calculator/

Share: X · LinkedIn · Facebook · Hacker News · Email